ShortFlex - Average price history

UK – IntraFlex – Western Power Distribution


In the first phase, August-September 2020, WPD procured 50.15MW of flexibility services across 241 trades with large variety across them.
Some bids were matched within 10 minutes of being uploaded; others were matched less than two hours ahead of real time.

Average price UK:

Week 40 (21.-30.9.20):      166.98 GBP/MW/HH
Week 39 (17.-23.9.20):      
150.23 GBP/MW/HH
Week 38 (10.-16.9.20):       
162.00 GBP/MW/HH
Week 37 (3.-9.9.20):
           158.00 GBP/MW/HH
Week 36 (27.8-2.9.20):       150.00 GBP/MW/HH