UK – IntraFlex phase 2 – Western Power Distribution
2021
Week | Volume weighted average price (GBP/MW*h) | Min (GBP/MW*h) | Max (GBP/MW*h) | Net traded volume (MW*h) |
35 | 296.84 | 240.00 | 300.00 | 25.77 |
34 | 283.10 | 210.00 | 300.00 | 12.415 |
33 | 280.62 | 210.00 | 300.00 | 28.074 |
32 | 277.92 | 240.00 | 300.00 | 31.863 |
31 | 266.60 | 120.00 | 300.00 | 18.333 |
30 | 286.59 | 180.00 | 300.00 | 37.265 |
29 | 320.74 | 180.00 | 360.00 | 14.854 |
28 | 309.14 | 120.00 | 360.00 | 9.937 |
27 | 308.80 | 60.00 | 360.00 | 19.201 |
26 | 290.28 | 270.00 | 300.00 | 23.762 |
25 | 284.68 | 1.00 | 300.00 | 30.603 |
24 | 298.95 | 175.00 | 300.00 | 35.071 |
23 | 296.32 | 225.00 | 300.00 | 31.456 |
22 | 300.00 | 300.00 | 300.00 | 29.285 |
21 | 296.79 | 75.00 | 300.00 | 12.31 |
20 | 299.46 | 1.00 | 300.00 | 23.465 |
19 | 300.00 | 300.00 | 300.00 | 24.143 |
18 | 299.02 | 1.00 | 300.00 | 22.48 |
2020
In the first phase, August-September 2020, WPD procured 50.15MW of flexibility services across 241 trades with large variety across them.
Some bids were matched within 10 minutes of being uploaded; others were matched less than two hours ahead of real time.
Average price UK:
Week 40 (21.-30.9.20): 166.98 GBP/MW/HH
Week 39 (17.-23.9.20): 150.23 GBP/MW/HH
Week 38 (10.-16.9.20): 162.00 GBP/MW/HH
Week 37 (3.-9.9.20): 158.00 GBP/MW/HH
Week 36 (27.8-2.9.20): 150.00 GBP/MW/HH